Floor strengthening — securing and load transfer
Strengthening timber, concrete and steel-joist floors: change of use, sagging floors, renovation.
A floor needs strengthening when it must carry more than it was designed for, or no longer carries what it should: deflection, vibration, decayed or corroded beams. The solution depends on its structure, timber, concrete or steel joists, and on the structural engineer’s design.
Adapting a floor to new loads and uses
What is floor strengthening?
A residential floor is designed for an imposed load of 1.5 kN/m² (Eurocode 1); offices require 2.5, shops 5. Converting a home into offices, fitting out an attic or installing a library, a cast-iron bath or an indoor pool therefore means checking, and often strengthening, the existing floor.
Techniques follow the structure: doubling or sistering the joists of a timber floor, a composite concrete slab cast over the floor, steel beams or sections added underneath, repair of corroded joists in a jack-arch floor, common in older buildings in Nice. Strengthening is always preceded by investigation and a structural calculation.
When to strengthen a floor
Every case starts with investigation and a structural calculation.
Sagging or bouncy floor
Visible deflection, a springy feel, cracking floor tiles.
Change of use
A home converted into offices or a shop, an attic fitted out.
Heavy point load
Library, bath, tank, technical equipment.
Decayed timber
Joists weakened by insects or damp.
Corroded steel joists
Jack-arch floor whose steel joists have rusted.
Stairwell or opening
A stairwell cuts joists or reinforcement that must be picked up.
Our expertise
Know-how in special works
We strengthen timber, concrete and steel-joist floors, carrying out the solutions designed by the structural engineer.
- Strengthening of timber and concrete floors
- Load transfer
- Installation of beams and steel sections
- Strengthening of existing structures
- Work on occupied sites
How a Sirianni Travaux project unfolds
Investigation and survey
Type, spans and condition of the floor, current and future loads.
Structural calculation
The engineer sizes the strengthening and the sequence of works.
Propping and works
Propping where needed, then installation of the strengthening.
Handover
Inspection of the strengthening before the props are removed.
Frequently asked questions
When should a floor be strengthened?
Which floors can be strengthened?
Is the strengthening visible?
Can I stay in my home during the works?
Is approval needed in a co-owned building?
Related services
Stairwell openings
Stairwell openings in concrete, timber or steel-joist floors, with trimmer frame and propping.
ViewConcrete & masonry repair
Repair of damaged concrete and masonry: corroded reinforcement, cracks, joints, old walls.
ViewLoad-bearing wall openings
Specialists in load-bearing wall openings for renovation and construction.
ViewA consolidation or foundation project?
Get a tailored assessment for your special works. Tell us about your structural issue or your project — we will get back to you after analysing the structure and its surroundings.